TM 1-4920-434-13&P
0045 00
INSPECTION OF INSTALLED ITEMS CONTINUED
MILLING/DRILLING MACHINE MOUNTING HARDWARE CONTINUED
NOTE
During installation of components same hardware should be used so as to maintain original
integrity of shop set.
1.
Inspect milling/drilling machine (Figure 4) for damage. Replace as necessary.
2.
Inspect milling/drilling machine hardware (Figure 4, Item 2, 3, 5, 6, and 7) for rust, cracks and rounded heads.
Replace as necessary.
REMOVAL
Remove two bolts (Figure 4, Item 2), two upper lat washers (Figure 4, Item 3), two lower lat washers (Figure
4, Item 5), two lock washers (Figure 4, Item 6), and two nuts (Figure 4, Item 7) removing milling/drilling machine
(Figure 4, Item 1) from shelf cabinet (C) (Figure 4, Item 4).
INSTALLATION
Install two bolts (Figure 4, Item 2), two upper lat washers (Figure 4, Item 3), two lower lat washers (Figure 4, Item
5), two lock washers (Figure 4, Item 6), and two nuts (Figure 4, Item 7) attaching milling/drilling machine (Figure
4, Item 1) to shelf cabinet (C) (Figure 4, Item 4).
END OF WORK PACKAGE
0045 00-5/6 blank