TM 1-4920-445-13&P
0040 00
INSTALLATION CONTINUED
SHELF CABINET (F) (SC4930-99-B70) CONTINUED
2.
If a new work surface (Figure 8, Item 5) must be installed:
a.
Position work surface (Figure 8, Item 5), inished side up, on top of shelf cabinet (F) (Figure 8, Item 6).
b.
Ensure work surface (Figure 8, Item 5) is lush with back side of cabinet with a two inch over hang on the
front side of cabinet. Work surface (Figure 8, Item 5) should over hang 15 inches on left and right side of
cabinet.
c.
On inside of shelf cabinet (F) (Figure 8, Item 6), mark eight hole placements in top of cabinet on non-
inished side of work surface (Figure 8, Item 5).
d.
After eight hole placement marks have been made, lip work surface (Figure 8, Item 5) over with non-
inished side up.
e.
On non-inished side of work surface (Figure 8, Item 5) at eight marked hole placements, center punch
and drill eight 5/16 inch holes to a depth of 3/4 inch.
f.
Return work surface (Figure 8, Item 5) inished side up, on top of shelf cabinet (F) (Figure 8, Item 6).
3.
Align bolt holes of work surface Figure 8, Item 5) with bolt holes on top of shelf cabinet (F) (Figure 8, Item 6).
4.
Install eight lag bolts (Figure 8, Item 1), eight lock washers (Figure 8, Item 2), six large lat washers (Figure 8,
Item 3), and two small lat washers (Figure 8, Item 4) attaching work surface (Figure 8, Item 5) to shelf cabinet
(F) Figure 8, Item 6).
5.
Install hardware attaching shelf cabinet (F) (Figure 8, Item 6) to shelter loor IAW WP 0041 00, Cabinets (F)
Hardware, INSTALLATION.
6.
Install drawers, slides, and shelves as necessary IAW Drawers, Slides, And Shelves, INSTALLATION.
7.
Install kick plate IAW Kick Plate, INSTALLATION.
END OF WORK PACKAGE
0040 00-23/24 blank