TM 1-4920-445-13&P
0041 00
INSTALLATION
CABINETS (A) AND (B) HARDWARE
1.
Install ive bolts (Figure 1, Item 1), ive lock washers (Figure 1, Item 2), and ive lat washers (Figure 1, Item
3) attaching shelf cabinet (A) (Figure 1, Item 4), four drawer cabinet (A) (Figure 2, Item 9), six drawer cabinet
(B) (Figure 1, Item 8), four drawer cabinet (C) (Figure 1, Item 7), and four drawer cabinet (D) (Figure 1, Item
6) to shelter wall.
2.
Install four bolts (Figure 1, Item 1), four lock washers (Figure 1, Item 2), and four lat washers (Figure 1, Item
3) attaching two cabinet brackets (Figure 1, Item 5) to shelter loor.
3.
Install slides, drawers, and shelves as necessary IAW WP 0040 00, Drawers, Slides, And Shelves,
INSTALLATION .
4.
Install kick plate IAW WP 0040 00, Kick Plate, INSTALLATION.
5.
Torque bolts (Figure 1, Item 4) 160-190 in. lbs.
INSPECTION OF INSTALLED ITEMS
CABINETS (E) HARDWARE
Figure 2.
Cabinets ( E) Hardware .
Inspect cabinet assembly integration hardware (Figure 2) for rust, cracks and rounded heads. Replace as nec-
essary.
REMOVAL
CABINETS (E) HARDWARE
Remove four bolts (Figure 2, Item 3), four lock washers (Figure 2, Item 4), and four lat washers (Figure 2, Item
5) detaching two cabinet brackets (Figure 2, Item 2) from shelter loor.
0041 00-3