NOTE
During installation of components same hardware should be used so as to maintain original
integrity of shop set.
INSPECTION OF INSTALLED ITEMS
10 TON PRESS AND HARDWARE
Figure 1.
10 Ton Press.
1.
Inspect 10 ton press (Figure 1, Item 1) and hand pump (Figure 1, Item 8) for damage. Replace as necessary.
2.
Inspect 10 ton press hardware (Figure 1, Item 2, 3, 4, 5, 6, 7, 9, 10, 11, 12, and 13) for rust, cracks and
rounded heads. Replace as necessary.
REMOVAL
1.
To remove 10 ton press (Figure 1, Item 1), remove four bolts (Figure 1, Item 13), four upper lat washers
(Figure 1, Item 12), four lower lat washers (Figure 1, Item 9), four lock washers (Figure 1, Item 10) and four
nuts (Figure 1, Item 11).
0052 00-2