8.
While holding hinged sidewall, remove two sidewall support braces and store in shelter BII box.
WARNING
DO NOT get caught between cable and sidewall panel. DO NOT attempt to steady sidewall
panel if it is accidentally dropped. Trapped air acts as a cushion supporting sidewall panel.
Failure to observe warning could result in SERIOUS INJURY to personnel.
9.
Fold down hinged sidewall onto hinged loor. Allow wall to free fall before it comes to same plane as cables.
RAISING HINGED FLOOR
WARNING
Fold-out loor support cables must be secured in cable housings prior to raising shelter loor
from its lowered position to its level position. If support cables are not secured, support cables
will remain under tension. DO NOT attempt to remove cables if support cables are not secure.
Removing support cables while under tension could cause SERIOUS INJURY to personnel.
Figure 7.
Load Balancers Slide Stops, Upper Position.
1.
Remove lockout pins (Figure 7, Item 4) from lower position on both load balancers (Figure 7, Item 3).
2.
Open slide stops (Figure 7, Item 1) against support cables (Figure 7, Item 2) on both load balancers (Figure
7, Item 3).
3.
Replace lockout pins (Figure 7, Item 4) in upper position on both load balancers (Figure 7, Item 3).