0005 00
TM 1-4920-445-13&P
POSITIONING ROOF AND HINGED END WALLS CONTINUED
WARNING
When all equipment and materiel are stored on stationary side of shelter, limited loor
space presents a safety hazard to personnel. This is most critical during raising and
lowering of roof panel. Personnel inside shelter could become trapped between roof
panel and equipment bolted to loor. Failure to observe warning could result in SERIOUS
INJURY to personnel.
To avoid INJURY, a minimum of four personnel are required to perform all of the following
procedures.
Figure 12.
Raising Hinged Roof.
NOTE
Two personnel outside shelter must lift roof panel far enough to allow two people inside to
perform following steps:
2.
Lift roof panel (Figure 12, Item 1).
3.
Release two support strut assemblies (Figure 12, Item 3) from roof panel and extend them to full length.
4.
Insert pin (Figure 12, Item 2).
0005 00-12