0045 00
TM 1-4920-445-13&P
INSTALLATION CONTINUED
VACUUM SYSTEM MANIFOLD KIT ASSEMBLY CONTINUED
17. Slide heat shrink (Figure 1, Item 13) over slip coupling (Figure 1, Item 19) and 45 elbow tubing (Figure 1,
Item 18) joint.
18. Install 45 elbow tubing (Figure 1, Item 18) into slip coupling (Figure 1, Item 19) so that opening faces ceiling.
19. Slide heat shrink (Figure 1, Item 13) over 45 elbow tubing Figure 1, Item 18) and slip coupling (Figure 1, Item
19) joint.
20. Slide heat shrink (Figure 1, Item 13) over 45 elbow tubing (Figure 1, Item 18).
21. Install 90 elbow tubing (Figure 1, Item 1) to 45 elbow tubing (Figure 1, Item 18) so that opening faces cargo
end wall.
22. Slide heat shrink (Figure 1, Item 13) over 90 elbow tubing (Figure 1, Item 1) and 45 elbow tubing (Figure 1,
Item 18Figure 1, Item 1) joint.
23. Slide heat shrink (Figure 1, Item 13) over 90 elbow tubing Figure 1, Item 1).
24. Install 36 inch galvanized tubing (Figure 1, Item 3) into two bottom load clamping hangers (Figure 1, Item 2)
with two screws (Figure 1, Item 4) and two nuts (Figure 1, Item 5).
25. Install 36 inch galvanized tubing (Figure 1, Item 3) to 90 elbow tubing (Figure 1, Item 1).
26. Slide heat shrink (Figure 1, Item 13) over 90 elbow tubing (Figure 1, Item 1) and 36 inch galvanized tubing
(Figure 1, Item 3) joint.
27. Slide heat shrink (Figure 1, Item 13) over 36 inch galvanized tubing (Figure 1, Item 3).
28. Install non-threaded opening of adapter tee (Figure 1, Item 9) to 36 inch galvanized tubing (Figure 1, Item 3)
so that threaded opening of adapter tee (Figure 1, Item 9) faces the loor.
29. Slide heat shrink (Figure 1, Item 13) over 36 inch galvanized tubing (Figure 1, Item 3) and adapter tee (Figure
1, Item 9) joint.
30. Wrap threads of 1.5 inch inlet valve (Figure 1, Item 12) with thread tape.
31. Install 1.5 inch inlet valve (Figure 1, Item 12) to adapter tee (Figure 1, Item 9) so that lap opens toward ixed
sidewall.
32. Slide heat shrink (Figure 1, Item 13) over 36 inch galvanized tubing (Figure 1, Item 10).
33. Install 36 inch galvanized tubing (Figure 1, Item 3) into bottom load clamping hanger (Figure 1, Item 2) with
one screw (Figure 1, Item 4) and one nut (Figure 1, Item 5).
34. Install 36 inch galvanized tubing (Figure 1, Item 10) to adapter tee Figure 1, Item 9).
35. Slide heat shrink (Figure 1, Item 13) over adapter tee (Figure 1, Item 9) and 36 inch galvanized tubing (Figure
1, Item 10) joint.
36. Slide heat shrink (Figure 1, Item 13) onto 36 inch galvanized tubing (Figure 1, Item 10).
37. Install elbow (Figure 1, Item 11) to 36 inch galvanized tubing (Figure 1, Item 10) so that threaded end faces
the loor.
38. Slide heat shrink (Figure 1, Item 13) over 36 inch galvanized tubing (Figure 1, Item 10) and elbow (Figure 1,
Item 11) joint.
39. Wrap threads of 1.5 inches inlet valve (Figure 1, Item 12) with thread tape.
40. Install 1.5 inches inlet valve (Figure 1, Item 12) to elbow (Figure 1, Item 11) so that lap opens toward ixed
sidewall.
41. Shrink down ten pieces of heat shrink (Figure 1, Item 13) using heat gun.
42. Prime and paint IAW TM 43-0139.
END OF WORK PACKAGE
0045 00-4